Test Execution Example

This example presents how Eiffel events sent as part of a test activity can be connected.

Introduction

Using Eiffel events to describe the execution of a test activity can be done in wide variety of ways and with varying numbers of events. On one extreme, a test activity can be described with Eiffel activity events only, and on the other extreme a test activity can be expanded to send a big set of Eiffel events revealing the inner details of the test activity. Which way to choose depends on the complexity of your test execution system and on the need to describe and visualize the nitty-gritty details of the test activity.

The Eiffel protocol provides several events to use within a test activity. This example shows how to make use of most of the Eiffel events related to test activities, with the purpose to present how they all are related.

To understand the example provided here, it is important to explain a few concepts (used in the sequence diagram below). While Eiffel does not make any assumptions about the underlying infrastructure and/or testing methodology, it does encourage separation of concerns. In this example, it is not the responsibility of the Activity Orchestrator (e.g. the CI server) to determine the contents of the test scope, nor is it the responsibility of the Test Executor. Instead, the EiffelTestExecutionRecipeCollectionCreatedEvent makes it possible for a third actor, the Test Manager, to determine the test scope. A fourth actor, Environment Provider, is used to provide a test environment based on the needs described in the EiffelTestExecutionRecipeCollectionCreatedEvent. The Environment Provider has full control over all available test environments, and therefore the Test Executor SHALL use the provided environment to run the tests towards.

About the Example

In the example outlined here we assume that one test suite (a set of test cases) is to be executed in two different environments within the same test activity. The test suite consists of only two test cases, A and B, to keep the complexity of the event graph down. For the same reason issue verification is only performed for the test cases in environment 2.

Event Graph

alt text Dashed event links are optional and solid event links are mandatory.

Event-by-Event Explanation

ActT, ActS, ActF

EiffelActivityTriggeredEvent, EiffelActivityStartedEvent and EiffelActivityFinishedEvent are the top level events describing the status of the complete activity execution. ActT probably links to a previous event using a CAUSE link showing why this activity was triggered.

TERCC

The EiffelTestExecutionRecipeCollectionCreatedEvent event is sent to provide information about the contents of a test activity.

TSS

The EiffelTestSuiteStartedEvent signals that the execution of a set of test cases has started. The test cases defined as recipes in the EiffelTestExecutionRecipeCollectionCreatedEvent can be grouped to an arbitrary number of test suites. There should anyway always be one main test suite encapsulating all test cases in the activity.

TSF

The EiffelTestSuiteFinishedEvent reports that the execution of the test suite is finished. This event should be sent when all test cases in the suite have finished executing. The TSF event could contain a combined verdict and conclusion for all included test cases.

ED1, ED2

Here we assume that the test orchestrator has decided to split the complete set of test cases in two groups, each requiring their own test environment.

For each test environment set up and/or created an EiffelEnvironmentDefinedEvent event SHALL be sent. The environments could be static and thereby reused between a lot of test activities, or they could be created in runtime for every test activity. The latter is the typical case when testing in a cloud environment. The information needed to set up or create a test environment could be given in the TERCC event.

ArtC/CDef

To track what item is being tested there SHALL be a link to either an EiffelArtifactCreatedEvent or to an EiffelCompositionDefinedEvent from each test case triggered. What the ArtC/CDef event links to is left out from this example, but it could for example be a CAUSE link to another activity.

TCTx

To signal that a test case is about to be executed an EiffelTestCaseTriggeredEvent can be sent. The TCT events in this example link to the EiffelTestSuiteStartedEvent to enable tracking of the context in which the test cases are to be executed.

TCSx

EiffelTestCaseStartedEvents declare that test case executions have started. They should link to the environment in which they are executed.

TCFx

EiffelTestCaseFinishedEvents report the verdict and conclusion of their respective test case executions.

IVx

EiffelIssueVerifiedEvents are used to communicate the fact that a certain issue (e.g. a requirement or a bug report) has been verified successfully or not. The verification is in this example linked to a EiffelTestCaseFinishedEvent to describe what test case that was used to verify this issue. Just as for EiffelTestCaseStartedEvents, the IV events should link to the environment in which the issue is verified (it must not be the same environment as the linked test case).

CLM

A EiffelConfidenceLevelModifiedEvent is sent to declare what level of confidence was reached for the given item under test. It COULD link to the executed test suite to track what tests where performed to achieve the given confidence level.

Test Activity Execution Implementation

To realize the event graph in this example, a sequence like the following is needed: alt text

  1. A test activity gets triggered by some event or timer. An EiffelActivityTriggeredEvent is immediately sent, and when the activity is ready to be executed an EiffelActivityStartedEvent is sent. Depending on the CI Server used these events might come directly after each other, or if the CI Server has an execution queue internally the first event will be sent when the activity is put in the queue and the latter when the execution starts.
  2. In a simple test activity the list of test cases to be executed could be hard coded, but in this example we show how Eiffel events can be used to handle dynamic selections of test cases. The Test Manager is queried for the list of test cases together with the constraints on the test environment for those test cases. This information is all included in a TERC document represented by the EiffelTestExecutionRecipeCollectionCreatedEvent.
  3. A Test Orchestrator is called to separate the concerns of managing a CI activity from the test orchestration. This could of course be performed within the Activity Orchestrator unless there is a certain need to divide them. It is perfectly fine to deploy these two servers on the same physical node, if appropriate.
  4. The Test Orchestrator sends an EiffelTestSuiteStartedEvent referencing the EiffelTestExecutionRecipeCollectionCreatedEvent and EiffelActivityTriggeredEvent events to inform that the test execution is progressing. The batches of test case recipes in the TERC are evaluated and test suites are formed based on for example test environment needs.
  5. In a simple test activity there might not be a need to call a separate service to setup a test environment, but in this example we show how Eiffel events can be used to handle on demand created test environments. The provisioning of test environments could also be performed by the Test Executor, but in this example we show how to separate environment provisioning, connected to test case grouping, from the actual execution of the test cases. If a new test environment is created for this specific test suite an EiffelEnvironmentDefinedEvent is issued. If a previously created environment is used, its corresponding EiffelEnvironmentDefinedEvent is looked up.
  6. For each test case in the group a EiffelTestCaseTriggeredEvent is sent. A Test Executor is then called with the environment instance and the list of test cases to execute. The Test Executor executes the test cases and sends corresponding EiffelTestCaseStartedEvents and EiffelTestCaseFinishedEvents for each of them. The EiffelTestCaseStartedEvents shall refer to the environment in which the test case is executed, represented by its EiffelEnvironmentDefinedEvent. Whether the test suites are executed in parallel or in serial is of no interest to the Eiffel protocol. It's merely up to the test executor to handle it in the best way available.
  7. The used test environment is released. If a test execution is not finished within a certain timeout or on other condition, the Test Orchestrator could send an EiffelTestCaseCanceledEvent prior to releasing the environment.