We completed the milestone, work is progressing as expected. Overall, I'd say everything went well.
The frontend tests for Milestone 1 couldn't be completed by the due date, and moved to Milestone 2. This is because of us requiring to create new components in the initial milestones, which may lead to more frontend tickets per milestone and more time than anticipated. We may see some delay in the first few milestones, and would have to take that into account. Milestone 2 currently has 7 frontend tickets. I'm estimating frontend work for Milestone 2 to complete by 6th or 7th July. I'm glad the deadline is moved to 12th. However, Milestone 3 has a lot of work on the frontend, and may get delayed.
No blockers. May have questions on file import API changes.
None. |
Beta Was this translation helpful? Give feedback.
-
Milestone completed! Also, getting feedback on the type inference work and record filtering decisions was nice.
Nothing specific comes to mind.
Will need some additional details before starting record grouping work.
None. |
Beta Was this translation helpful? Give feedback.
-
|
Beta Was this translation helpful? Give feedback.
-
We're getting into a good cadence of work. We completed our first milestone, which is great. Design is a few milestones ahead, and backend is getting there.
Personally, I need to balance code work and non-code work better, I need to do a lot of different types of work and it's been harder than expected to find good stretches of time to focus on code work. I'll continue iterating on that.
No, I'll comment on individual people's responses with any questions. |
Beta Was this translation helpful? Give feedback.
-
It was a good week. I can feel how the simplified design specs allow me to submit things to review sooner. Feels much more manageable to embed the Figma prototypes rather than static screenshots.
I could communicate better when I introduce future features into my prototypes and be more clear about the reasons for doing so (anticipating needs, etc.)
No.
Not for now. |
Beta Was this translation helpful? Give feedback.
-
Retrospective
This covers work since our last discussion on 2021-06-23.
Product
Design
Development
sqlalchemy-filters
Infrastructure
Active Work
This is work planned for the upcoming week.
Product
Design
Development
sqlalchemy-filters
Infrastructure
Updates and Questions
Beta Was this translation helpful? Give feedback.